A9 update
Earthworks are progressing for the construction of the verges underneath the A9 overbridge.

Street light duct installation underway at west roundabout.

Surfacing of the non-motorised user path between Redgorton and A9 northbound bus stop.
![]() | ![]() | ![]() |
Excavating in preparation for construction of sign post foundations.
![]() | ![]() |
Tay Crossing Update
Concrete pour for the second section of the Tay Crossing West pier.
![]() | ![]() |
Installation of the piles is continuing at the Tay Crossing west abutment.

Works have been continuing on the construction of the traveller system and temporary props which will be used to construct the Tay Crossing concrete deck.
![]() | ![]() |
Link Road Update
Ducting installation underway between Stormontfield and Tay Crossing.
![]() | ![]() |
Sign post installation underway at A93 roundabout

Surfacing for non-motorised path between Highfield roundabout and A93 ongoing