Project Update – September 11th 2023
A9 update
Cover surveys carried out for A9 overbridge deck.

Earthworks to form drainage ditches along Redgorton access road

Surfacing of the non-motorised user path from bus stop on southbound side of A9.
![]() | ![]() |
Concrete for construction of sign post foundations.

Installation of crash barrier along south bound A9 carriageway.

Tay Crossing Update
Construction underway of formwork for east pier bridge hammerhead.
![]() | ![]() |
Works have been continuing on the construction of the traveller system and temporary props which will be used to construct the Tay Crossing concrete deck on the west pier side.
![]() | ![]() |
Link Road Update
Earthworks underway for construction of footpath on A94 northbound towards roundabout.

Earthworks for link road verges complete.

Stormontfield Road Roundabout surfacing completed and white lining commenced.
