Project Update – May 22 2023
A9 update
Building up west merge and diverge slip roads to top of stone level, ready for cement-bound granular material subbase to be laid.


Laying tarmac on north and southbound carriageways.


A9 overbridge concrete pour for bridge deck


Tay Crossing Update
Preparing for east pier pile cap concrete pour.


Link Road Update
Installation of drainage manhole, near A93 roundabout.


Drainage installation near Highfield roundabout.