Project Update – March 8 2023

8th March, 2023
CTLR Updates

A9 update

Foundations poured and cement-bound granular material (CBGM) Rig Set up

4-way BT and communications ducting installed at southbound side

GB Landscaping tree planting at Bertha Cut

A9 overbridge piling on east and west sides.


Tay Crossing Update

Piling operation continuing on both side of the Tay, with 24 piles completed on the east pier and 6 completed on the west.

West abutment stem wall formwork ongoing.


Link Road Update

Arch beam bearing pads poured at Green Bridge, ready for precast arches to be installed.

Drainage squads installing 150mmØ pipe road crossing at Stormontfield Road