Project Update – July 31st 2023
A9 update
Earthworks around eastern slip road of A9 overbridge.
Traffic management lifted and opening of both carriageways.
Installation of crash barriers for southbound carriageway.
Installation of drainage under A9 overbridge.
Tay Crossing Update
Transporting stem concrete pour shutters from east side to west side in preparation for west pier stem pour.
Completion of concrete pour for west pier pile cap.
Installation of piles for west abutment.
Stripping formwork for east pier stem concrete pour.
Construction of steel reinforcement in preparation for west pier stem concrete pour.
Link Road Update
Tarmac being laid around Highfield roundabout.
Construction of west side of new A94 allignment and roundabout.]
Construction of cycle/footpaths between Highfield roundabout and A93.
Construction of cycle/footpaths between A94 and Highfield.