Project Update - March 15 2023

16th March, 2023
CTLR Updates

A9 update

A9 Overbridge backfilling east abutment


A9 Overbridge west abutment stem wall poured


A9 Overbridge all 8 columns now poured

Tay Crossing Update

Last pile on east pier being poured

Piling rig moved from east pier moved over to West side

Link Road Update

First four sections of green bridge deck installed

Scottish water diversion installation

A94 road plaining