Project Update – August 7th 2023
A9 update
Earthworks around eastern slip road of A9 overbridge.
Installation of drainage along A9 overbridge eastern slip road.
Tay Crossing Update
Construction of platform for concrete pump in preparation for first west pier stem pour.
Installation of piles for west abutment.
Stripping scaffoling for east pier stem concrete pour.
Link Road Update
Road closure and construction of new Stormontfield roundabout and approach road.
Construction of west side of new A94 allignment and roundabout.
Topsoiling verges between Highfield roundabout and A94.