Project Update – 01 December 2023
A9 update
West Roundabout – mono block on going, roundabout ducting.
George Walker installing crash barrier – South bound on slip road
Tay Crossing Update
Tay Crossing – West side – CFT preassembly
Tay Crossing – West pier hammerhead PT ducting installation for pour 3
Link Road update
NMU Bridge – backfilling – ongoing
Stormontfield box cut for road and footpath