Cross Tay Link Road – Progress Report, 31 August, 2022
Work is progressing fast on the new main site compound on Stormontfield Road near Old Scone. Fencing is complete and the car park is ready for surfacing
Capping almost complete on A93 to A94 section Capping layer materials help to reduce costs and to protect the subgrade from rainfall and weathering and improve the stiffness of the road
Work continues on the access road for construction of the new bridge on the east side of the railway.
Concrete pour on the A9 in preparation for installation of temporary pedestrian diversion.